PG&E gas safety project update

The gas line replacement project is estimated to be completed mid-December.

The estimated completion of PG&E's gas line replacement project along Junipero Serra Boulevard on Stanford lands has been moved to mid-December.

PG&E has received approval from the County of Santa Clara to work during the following hours:

  • Campus Drive West to Alpine Road: currently only night time work, however the county has approved 22 hours per day, 9 a.m. to 7 a.m., Monday through Saturday; 8 p.m. to 5 a.m. Sunday.
  • Campus Drive East to Page Mill Road: 12 hours per day, 9 a.m. to 9 p.m., Monday through Friday; 8 a.m. to 9 p.m. Saturday.
  • Staging area at Page Mill Road and Junipero Serra Boulevard: 24 hours per day to access equipment and materials.

"This will add another day to our schedule and help get the work done more quickly," said Eric Jansen, a PG&E accounts manager. Jansen noted that the hours indicated are the approved hours, and that crews may or may not be working during all those shifts.

In the event of questions or concerns about this work, contact Denise Alexander with PG&E Customer Impact at denise.alexander@pge.com or (415) 516-0238.